MINISTERS IN CHARGE OF ENERGY VISITS THE 80MW RUSUMO PROJECT TO ASSESS THE PROGRESS
Saturday, 30 September 2023
Ngara/Tanzania, The 15th council of Ministers in charge of Energy from Rwanda, Burundi and Tanzania convened to assess the progress of construction works of the Regional Rusumo Falls Hydroelectricity project, which is at 99.7%.
The first unit of 27MW was successfully tested, whereas the remaining two machines has to be tested before end of October 2023 with expectation to officially inaugurate the facility in December 2023 once all units are on national grids of the respective member states.
The 15th Council of Ministers was chaired by the minister of energy in the United Republic of Tanzania Dr. Doto Biteko who serves also as the Deputy Prime Minister. The council calls for combined efforts and team works sprit to fast-track the project completion.
The Regional Rusumo Falls Hydroelectric Project (RRFHP) is connecting the plant’s facilities upstream in Tanzania and downstream of the switchyard on Rwanda side and will contribute to having lower energy costs in shareholder countries.

Hon. Minister of infrastructure Dr. Jimmy Gasore in midst between Ministers in charge of Energy from Burundi and Tanzania, during the site visit.
The project is owned by Rusumo Power Company Limited (RPCL), a joint development of Rwanda, Burundi and Tanzania.
Rusumo project is pioneering as it gives back to riparian communities surrounding Rusumo project’s construction area by implementing the Local Area Development Program (LADP), a benefit-sharing program designed to enhance regional economic and social development in the Rusumo area as an extended program related to the construction of Rusumo project.
On Rwanda side, the LADP program is implemented in Kirehe and Ngoma district whereby various infrastructure projects have been constructed, among include: Kigina health center, rehabilitation of 30 km of feeder roads in Kigarama and Musaza, Cyasarabwayi-Nganda road in Kirehe district.
Whereas, in Ngoma district the construction of 33 km of Gituku-Murama water supply and 28,7 km of mixed water pipeline supplying 10, 500 populations of Gatonde-Gahima cells.
The overall project progress of the Power Plant construction is at 99.7%with 99.8% progress for hydro mechanical and civil works and 99.5% for the electromechanical.
Topics
Nyabihu, 6 September 2026, The Government of Rwanda is strengthening efforts to ensure that critical infrastructure remains resilient to…
Nairobi, Kenya – 6 October 2026 - Rwanda and Kenya have strengthened bilateral cooperation in housing and urban development through the signing of a…
Mombasa, Kenya – 29 September 2026: Rwanda and Kenya marked a significant milestone in their energy cooperation with the arrival of the MT Sea Wolf,…
Rwamagana, 23 September 2026, the ongoing construction and rehabilitation of the Karenge Water Treatment Plant (WTP) in Karenge Sector, Rwamagana…
KIGALI, RWANDA, Minister of State in the Ministry of Infrastructure, Armand Zingiro, has called for stronger investment, innovation, partnerships and…
KIGALI, RWANDA, The Government of Rwanda has officially commenced the construction works for the expansion and upgrading of the Prince…
Kigali, Rwanda 11 August 2026: Minister of Infrastructure Damien Murwanashyaka carried out a working visit to assess the implementation and progress…
Musanze, 11th August 2026, The Ministry of Infrastructure, in partnership with development partners in the urbanisation sector, convened a three-day…
Rwanda has called for stronger political leadership, innovative financing and institutional reforms to accelerate the transformation of water and…