Nyabarongo II Hydro Power Project gets US$ 214 million financing boost
Kigali February 7, 2020: The Government of Rwanda and the People’s Republic of China today signed a framework agreement that will allow China, through China Exim Bank to extend a concessional loan worth US$ 214 million (approximately Frw 203 billion) that will facilitate the construction of Nyabarongo II Hydropower Project.
Nyabarongo II Hydropower Project will have three components: 43.5 MW Hydro power plant, a Substation and 110KV transmission line covering 19.2 km from the Power Plant to Rulindo sub-station.
Once commissioned after a construction period of 56 months, the project will reduce reliance on non-renewable energy resources for electricity generation and contribute to the stability of the grid. Further to that, the project is expected to create jobs to Rwandans during and after construction of the power plant.
During construction peak period the project is expected to employ more than 700 Rwandans. The Project will also use domestic construction materials including sand, stones, wood, and cement among others. Only electrical and electromechanical equipment are expected to be imported.
“In addition to the current 224 MW generation capacity, combined with the pipeline of power projects, Nyabarongo Hydro II will increase grid generation capacity to an estimated 513.5 MW,” The Minister of Finance and Economic Planning Dr. Uzziel Ndagijimana said.
According to His Excellency RAO Hongwei, the Ambassador of the People’s Republic of China to Rwanda, this project will generate power, create job opportunities, improve irrigation and turn swamp into cultivatable land as large as large as twenty thousand hectares.
The hydro power project is expected to hasten Rwanda’s ambition to be among the first countries in Africa to achieve universal electrification and the first to achieve less than 50 percent reliance on traditional cooking fuels as enshrined in the National Strategy for Transformation (NST1).
The NST1 targets a generation capacity of 564 MW and today we have a total installed capacity of 224.63 MW of which, still more than 15% of it, is generated from diesel run generators which will be replaced.
There are several power plant projects in pipeline which are expected to bring more power on-grid. These include: 49 MW from Rusizi Hydro Power III where (147MW) will be shared between Rwanda, DRC and Burundi; 27 MW from Rusumo Hydro where 80 MW will be shared between Rwanda, Burundi and Tanzania; 80MW from Hakan Peat to Power Project; 50 MW from SYmbion Methane Gas Project and
40 MW expected to be generated from other Micro or Mini-Hydro projects which are at different development stages.
Topics
Kigali, 16th February 2026 - The Government of Rwanda has reaffirmed its commitment to strengthening rural connectivity as a catalyst for inclusive…
Thursday 22 January 2026, the Ministry of Infrastructure (MININFRA) hosted a ceremony in Kigali to formalize the signing of a Memorandum of…
Muscat, Oman, 11 January 2026: Oman Air, the national airline of the Sultanate of Oman, has announced the launch of direct flights to Kigali, Rwanda,…
Residents of the Rugerero Model Village, located in Rugerero Sector of Rubavu District, have expressed their appreciation to the Government of Rwanda…
In a landmark step toward realizing Rwanda’s Vision 2050 and the National Strategy for Transformation (NST-2), the Government of Rwanda has officially…
The Governments of Rwanda and Senegal have today signed a Bilateral Air Services Agreement (BASA) in Kigali, marking a historic step towards enhancing…
Minister of State for Infrastructure, Amb. Jean de Dieu UWIHANGAYE, conducted a comprehensive field visit from 26 August 2025, touring key…
Rusizi – June 9, 2025 – The Ruzizi III Regional Hydropower Project, a landmark $800 million initiative aimed at expanding energy access in Rwanda,…
On 5th June 2025, the Government of Rwanda official received provisionally the newly completed Rusizi II One Stop Border Post (OSBP) facility. This…